Project Name | CPP BANGLADESH SPM DOUBLE PIPELINE PROJECT |
End User | SENSIA UK LIMITED (EASTERN REFINERY LIMITED (ERL) |
Main Con | Applied Engineering Pte Ltd |
Scope of Work | Fabrication, installation and testing of Skid and piping |
Quantity | Prover Skid – 2 Units, Metering Skid – 2 Units |
Structure | 37 Tons, Piping : 4350 Dia-Inch |
Material | Structure – Carbon Steel S355 J0 Piping – Carbon Steel (API 5L Gr 52) |
Project Name : | HEAT EXCHANGER |
End User | P.T. ASAHIMAS |
Main Con | Applied Engineering Pte Ltd |
Scope of Work | Fabrication of Shell and Tube bundle |
Quantity | Shell and tube bundle – 1 Unit |
Material | Shell – Carbon Steel ID2400 x 40mmT x 17940 mm Lg Tube bundle – Stainless Steel tube Dia 8” x 24mmT |
Project Name | HEAT EXCHANGER |
End User | Singapore Refining Company |
Main Con | Applied Engineering Pte Ltd |
Scope of Work | Retubing of tube bundle |
Quantity | Tube bundle – 1 Unit ( OD ) |
Material | Tube – Carbon Steel Dia 1” x 2.77mm T |
Project Name | BUZIOS FIELD AREA DEVELOPMENT (P79) |
End User | PETROBRAS |
Main Con | Applied Engineering Pte Ltd |
Scope of Work | Fabrication of WAG Injection Well Pig Receiver |
Quantity | 10 Units |
Material | Super Duplex Stainless Steel (A790 UNS S32750 U A182-F53) |
Project Name | Vacuum Pump Skid Package 50KTA |
End User | Shell Eastern Petroleum (Pte) Ltd |
Main Con | Applied Engineering Pte Ltd |
Scope of Work | Fabrication, installation and testing of Skid and piping |
Quantity | 1 skid |
Material | Structure – Carbon Stee (S355 J0 ) Piping – Carbon Steel |