| Project Name | CPP BANGLADESH SPM DOUBLE PIPELINE PROJECT |
| End User | SENSIA UK LIMITED (EASTERN REFINERY LIMITED (ERL) |
| Main Con | Applied Engineering Pte Ltd |
| Scope of Work | Fabrication, installation and testing of Skid and piping |
| Quantity | Prover Skid – 2 Units, Metering Skid – 2 Units |
| Structure | 37 Tons, Piping : 4350 Dia-Inch |
| Material | Structure – Carbon Steel S355 J0 Piping – Carbon Steel (API 5L Gr 52) |


| Project Name : | HEAT EXCHANGER |
| End User | P.T. ASAHIMAS |
| Main Con | Applied Engineering Pte Ltd |
| Scope of Work | Fabrication of Shell and Tube bundle |
| Quantity | Shell and tube bundle – 1 Unit |
| Material | Shell – Carbon Steel ID2400 x 40mmT x 17940 mm Lg Tube bundle – Stainless Steel tube Dia 8” x 24mmT |

| Project Name | HEAT EXCHANGER |
| End User | Singapore Refining Company |
| Main Con | Applied Engineering Pte Ltd |
| Scope of Work | Retubing of tube bundle |
| Quantity | Tube bundle – 1 Unit ( OD ) |
| Material | Tube – Carbon Steel Dia 1” x 2.77mm T |

| Project Name | BUZIOS FIELD AREA DEVELOPMENT (P79) |
| End User | PETROBRAS |
| Main Con | Applied Engineering Pte Ltd |
| Scope of Work | Fabrication of WAG Injection Well Pig Receiver |
| Quantity | 10 Units |
| Material | Super Duplex Stainless Steel (A790 UNS S32750 U A182-F53) |


| Project Name | Vacuum Pump Skid Package 50KTA |
| End User | Shell Eastern Petroleum (Pte) Ltd |
| Main Con | Applied Engineering Pte Ltd |
| Scope of Work | Fabrication, installation and testing of Skid and piping |
| Quantity | 1 skid |
| Material | Structure – Carbon Stee (S355 J0 ) Piping – Carbon Steel |